Construction works of Nord Stream 2 pipeline to be finished in August

Vestnik Kavkaza – Construction works under the Nord Stream 2 gas pipeline project may be finished already in August, Matthias Warnig, managing director of Nord Stream 2 AG, the project operator, said in an interview with the Handelsblatt newspaper on Sunday.

“We believe that construction works will be over by the end of August,” he said, adding that the construction is 98% completed by now.

According to Warnig, three months will be needed to receive various certificates and undergo trials. The process has already kicked off in respect of the pipeline’s first line that has already been completed. Our goal is “to commission [the project] already this year,” he noted.

The new 1,230-kilometer pipeline, basically following the same route as Nord Stream, traverses the economic zones and territorial water of five countries, namely Russia, Finland, Sweden, Denmark, and Germany. Works under the project were suspended in December 2019 after Allseas, a Swiss company laying the pipes for the Nord Stream 2 pipeline, suspended pipe-laying works over possible US sanctions and recalled its ships. Works were resumed in December 2020.

Source